Total closure of Lax railway station

Now that most of the platforms have been rebuilt, the passenger subway is currently being built at Lax station during the total closure of the MGB. The challenging part is that the entire work has to be completed within 3 weeks. The ramps for the subway were already built in the summer, and now the part of the subway below the tracks is being built. Prefabricated concrete elements will be used and placed for this. Afterwards, the ballast will be applied and the new roadway will again be made ready for use so that trains can roll through the rebuilt station again on 15 November.