- Client: HRS
- Site management/reference person: HRS, Hamoudi Zinédine
- Site manager: Mathias Wyssen
- Foreman: Horst Theler
- Foremen: Peixoto Araujo Daniel, Raphael Wyssen
- Construction time: Shell construction from November 2021- August 2023
- Construction costs: 48 million
Technical data:
- 69'000m² formwork type 2
- 20'000m² formwork type 4.1
- 70'000m² slab formwork type 2
- 190m² circular formwork
- 6'900t reinforcement
- 57'600m³ concrete
- 1740 prefabricated columns
- 320 Prefabricated stairs
- 1125 Prefabricated walls
Project description:
A new urban quarter is being built in the heart of the city of Sion. This includes a parking garage with 625 parking spaces, a hotel with 100 rooms, a concert and congress hall with 600 seats, 5,800m2 of commercial space, 10,300m2 of office space and 302 apartments. The project covers a site of more than 16,000m2 and is due to be ready for occupation at the end of 2024.
The construction work was carried out by the consortium Walpen AG (30%), Dumas SA (30%) and Gebr. Zengaffinen (40%):
- Lead management: Zengaffinen Bros.
- Tech. Management: Walpen AG, Dumas SA and Zengaffinen Bros.
- Commercial management: Walpen AG
Requirements:
- High quality requirements
- Short shell construction time of around 18 months
- approx. 100 workers from the consortium incl. Subu on site
- Coordination in the construction management team
- Construction site is located directly next to Sion main station
- Construction site in the approach path of Sion airport
- Little installation space available