- Client: Municipality of Fiesch
- Site management / Reference person: BMI Architektur AG / Bruno Margelisch
- Project manager: Burgener Erhard
- Foreman: Faredin Salihi
- Construction time: October 2019 - November 2020
- Construction costs: 1 million
Technical data:
- Formwork walls & retaining walls: 1050 m²
- Reinforcement: 49t
- Concrete: 540 m³
Project description:
Due to the proximity of the existing buildings, the excavation pit was excavated in vertical stages using shotcrete and anchors. In the course of the excavation work, existing pipes had to be continuously relocated. On the one hand, adjustments were made to the existing complex and on the other, a new 3-storey building was constructed using conventional in-situ concrete construction methods.
Requirements
- Short construction time
- Pandemic measures