- Client: SBB Immobilien AG / Municipality of Visp
- Site management / Reference person: Frutiger GU, Thun
- Site manager / Foreman: Isler Rolf / Nef Pascal
- Construction time: August 2006 to June 2007
- Construction costs: CHF 7.1 million
Technical data:
- 110m building length
- 18m Building width
- 25m Building height
- 225m x 25m Parking
- 8'000m3 concrete
- 25'000m2 Formwork
- 920'000kg reinforcement
Project description:
New construction of a 5-storey reception and service building with parking garage and covered post bus transfer point. The construction work was carried out by the Walpen AG/Frutiger AG consortium. Lead management: Frutiger AG Technical management: Walpen AG / Frutiger AG Commercial management: Walpen AG Participation: Walpen AG 50 % / Frutiger AG 50 % Industrial construction Concrete approx. 8,000 m3 Formwork approx. 25,000 m2
Requirements:
- Very complex formwork work, especially the covered post bus transfer area
- Prefabricated columns (spun concrete) D=40 cm
- Eccentric supports in the parking lot
- Very ambitious schedule
- Construction without interrupting rail traffic at Visp station