- Client: Municipality of Bitsch
- Construction Manager / Reference Person: Municipality of Bitsch / Renato Berchtold
- Construction Foreman: Pierluigi D`Onofrio
- Foreman: Stefen Mosebach
- Construction time: September 2021 - March 2022
- Construction costs: CHF 270,000
Technical specifications:
- 400 m² of clearing work
- 1,300 m³ excavation
- 700 m³ rock excavation
- 100 m³ blasting rock
- 660 m cable conduit
- 610 m drinking water pipe cast iron Ø 150 mm
- 350 m pipelines
- 70 m micro bored piles
- 100 m³ UG 0/45
- 12 tons of pavement
- 4 tons of reinforcement
- 35 m³ concrete
Object description:
A drinking water pipe and a cable protection pipe had to be laid over a length of 660m. The steep terrain and the rock make the work difficult. A walking excavator had to be used to carry out the excavation work.
Special requirements:
- Working on steep terrain
- Protective measures Blasting work
- Rock stabilization
- Short construction time