Bitsch

Drinking water extension

  • Client: Municipality of Bitsch
  • Construction Manager / Reference Person: Municipality of Bitsch / Renato Berchtold
  • Construction Foreman: Pierluigi D`Onofrio 
  • Foreman: Stefen Mosebach
  • Construction time: September 2021 - March 2022
  • Construction costs: CHF 270,000

Technical specifications:

  • 400 m² of clearing work
  • 1,300 m³ excavation
  • 700 m³ rock excavation
  • 100 m³ blasting rock  
  • 660 m cable conduit
  • 610 m drinking water pipe cast iron Ø 150 mm
  • 350 m pipelines
  • 70 m micro bored piles  
  • 100 m³ UG 0/45
  • 12 tons of pavement  
  • 4 tons of reinforcement  
  • 35 m³ concrete

Object description:

A drinking water pipe and a cable protection pipe had to be laid over a length of 660m. The steep terrain and the rock make the work difficult. A walking excavator had to be used to carry out the excavation work.

Special requirements:

  • Working on steep terrain
  • Protective measures Blasting work  
  • Rock stabilization  
  • Short construction time