- Client: Barbara Zurschmitten & Florian Hirte
- Site management / Reference person: Chanton Marc / Machart architektur
- Site manager: D'Onofrio Pierluigi
- Foreman: Diego Barberi
- Construction time: October 2019 to September 2020
Technical data:
- 1,500 m3 excavated material
- 850 m2 wall formwork
- 150 m2 slab formwork
- 20 tons of reinforcement
- 200 m3 concrete
- 40 tons stone rolling
- 80 tons of asphalt
Project description:
An EFH with studio was built in Mörel. The construction consists of solid and timber construction. Very elaborate surroundings with several stone scrolls.
Requirements:
- Work on the site
- Immediate measures: shotcrete and anchor bolts
- Tight space conditions