Sierre

Hall Univerre

  • Client: Univerre Fabio Naselli
  • Site manager/reference person: Freddy Rieder
  • Foreman: Antonio D`Onofrio
  • Foreman: Pedro Oliveira
  • Construction period: April 2020 - April 2021
  • Construction costs: 2.8 million

Technical data:

  • 3000 m³ excavation
  • 3700 m³ concrete
  • 330 to. reinforcement
  • 5500 m² wall formwork
  • 200 m² slab formwork
  • 380 m² nail wall
  • 3000 m² XPS insulation
  • Prefabricated elements, floor slabs and concrete floor beams were supplied and installed on site.

Project description:

A new logistics building for the company Univerre is being built here on a floor area of 2100 m2. The floor slab is very elaborate, with recesses and several concrete beams. The building has a total of 3 storeys. All ceilings and load-bearing walls are made of in-situ concrete. Various prefabricated concrete parts such as ceiling slabs, concrete beams and stair elements are installed. The infill masonry is subsequently constructed in cement block masonry. All concrete surfaces are finished (mono concrete).

Requirements:

  • Very short construction time
  • Complex project with very complex logistics
  • High demands on occupational safety
  • Very complex formwork work (ceiling height and wall heights up to 9 meters)

Contact persons