- Client: Municipality of Baltschieder
- Construction Manager / Reference Person: Nicola Kalbermatten
- Construction Foreman: Mathias Wyssen
- Deputy foreman: Iwan Rieder
- Foreman: Diego Cathrein
- Construction time: May/2021 - Sept./2023
- Construction costs: CHF 11'000'000.-
Technical specifications:
- face concrete 9'000m3
- Mass concrete 10'000m3
- Reinforcement 1'300 tons
- Excavation 40'000m3
Object description:
On the construction site HWS Baltschiederbach the existing dam will be raised to protect the inhabitants of Baltschieder from future storms.
Special requirements:
- Wall formwork with up to 30 degrees of tightening.
- Special concrete types
- High walls
- Work near the river