- Client: Municipality of Gampel-Bratsch
- Site management / reference person: VWI Ingenieure AG, Nikola Vasilic
- Site manager / foreman: Jasin Ajeti / Nenad Dugic
- Construction period: May/2021 - July/2021, surfacing 2022
- Construction costs: 400'000.-
Technical data:
- 3,000m3 excavation / fill work
- 100m2 quarry stone masonry
- 500 to. Rolling of streambed base
- 400m3 Extraction of suitcase material on site
- 1'240m2 New connection to access / private road (asphalt work)
- 80m' surrounding / retaining wall
Project description:
The construction work includes the implementation of part of the construction measures required to ensure flood protection on the Tschingelbach in Niedergampel. A 4m wide overload corridor and a new embankment road were created on the Burketen, which will first be used as a construction slope and then as an access road. All removal, excavation and filling work was carried out using GPS and 3D-controlled machines.
Requirements:
- Material extraction on site
- Working in the danger zone
- Short construction time