Ferden

Immediate measures Milimatta

  • Client: Canton of Valais
  • Construction Foreman: Pierluigi D'Onofrio
  • Foreman: Anton Pfaffen
  • Construction time: June 2018 - November 2020
  • Construction costs: 500,000CHF

 

Technical specifications:

  • 200 m² shotcrete
  • 400 m² formwork type 4.1
  • 13 to reinforcement
  • 300 m³ concrete
  • 400 m³ Unbound mixtures 0/45
  • 400 m³ Cyclopean masonry

 

Object description:

Since the road is too narrow, it needs to be widened and provided with an additional crosswalk.

 

Special requirements:

  • Short construction time
  • Execution under traffic
  • Slope stabilization
  • Tight space conditions