- Client: Municipality of Brig-Glis
- Site management / Reference person: Ricci Architekten, Brig / Müller Isabell
- Site manager / Foreman: Hutkai Peter / Wyssen Gabriel
- Construction time: 6 months
- Construction costs: CHF 2.8 million
Technical data:
- 275 tons of reinforcement
- 8.00m high concrete walls
- 5.40m concrete ceiling (height)
- 8'800m2 Wall formwork
- 2'500m2 Slab formwork
- 325m2 Brick masonry
- 100m2 Cement block masonry
- 3'000m3 concrete
- 8'500m2 Exposed formwork type 2.1
- 3'800m3 excavation
Project description:
The project includes a 30x60 m field hockey pitch for a variety of uses, a curling area with four lanes, changing rooms and technical rooms as well as a hall for martial arts in a location that is close to the city center and therefore easily accessible for pedestrians. The traffic concept provides for connections to public transport and an adapted parking area.
Requirements:
- Short construction time
- Coordination with subcontractors
- Complex project