St. Niklaus VS

MGBahn TU Mattsand

  • Client: Matterhorn Gotthard Infrastruktur AG, Brig
  • Site management/reference person: Christian Heinzmann / MGB AG
  • Site manager: Adem Salihi / Celine Ludi
  • Foreman: Sebastian Schwery
  • Foreman: Daniel Maric
  • Construction period: May 2022/ in progress until November 2023
  • Construction costs: 5.30 million

Technical data:

  • 5100 m³ excavation trenches
  • 17000 m³ excavated substructure and superstructure
  • 285 m² shotcrete
  • 585 m anchors
  • 505 m micro bored piles
  • 890 m³ in-situ concrete
  • approx. 110000 kg reinforcement
  • 3250 m² formwork
  • 450 m² waterproofing
  • 4435 m³ gravel mixture
  • 4720 m³ fill and backfill
  • 950 m³ barrier layer
  • 1830 m³ crushed stone (ballast)
  • 2350 m drainage
  • 23 pcs. inspection chambers
  • 1480 m cable conduit block
  • 24 pcs. Cable shafts
  • 18 plinths
  • 44 pcs. Pole foundations
  • 65 tons of decking
  • 350 m railings
  • 330 m crash barrier

Project description:

The Mattsand total reconstruction project is located between St. Niklaus and Herbriggen over a length of 1235 m. The core element is the new construction of the crossing with additional structural measures for supplementary use. Due to signs of wear and tear, the substructure and superstructure must be renewed along the entire route. The track geometry will be optimized to maintain the clearance gauge, in particular the service route on both sides, by shifting the track a maximum of 40 cm towards the valley after the Bielzug culvert in the direction of Herbriggen. The drainage and the cable system (new signal box, NS & Telecom, safety systems) will be renewed along the entire route. Various engineering structures will be erected to realize the total reconstruction.

Requirements:

  • Work during rail operations
  • Work under traffic (railroad operation) with tight space conditions
  • Complicated logistics as a result of restricted access routes and handling areas
  • Two-shift operation (night and day work)

Contact person

Daniel Maric

Foreman

Adem Salihi

Department Manager Foundation Engineering

+41 79 755 23 92

+41 27 948 05 48

adem.salihi@volken-group.ch

Sebastian Schwery

Federal dipl. foreman

+41 79 197 20 39

sebastian.schwery@volken-group.ch