Visp

New construction DEFH D'Onofrio

  • Client: D'Onofrio Pierluigi & Antonio
  • Construction Manager / Reference Person: D'Onofrio Pierluigi & Antonio
  • Construction Foreman: D'Onofrio Pierluigi
  • Foreman: Elmar Pfammatter
  • Construction time: March 2020 - June 2020

 

Technical specifications:

  • 1'200 m³ excavated material
  • 1'300 m² wall formwork
  • 100m² exposed concrete type 3.1 BOK 2
  • 500m² slab formwork
  • 40to reinforcement
  • 400 m³ concrete
  • 200m² masonry brick

 

Object description:

In Visp a double EFH in solid construction was built. Due to large spans and cantilevered components, the stripping times had to be extended.

 

Special requirements:

  • Exposed concrete type 3.1 BOK 2 board structure
  • Start pandemic measures
  • Short construction time
  • Longer stripping times
  • Complex basic construction