Naters

Renovation Belalp- and Bahnhofstrasse

  • Client: Municipality of Naters
  • Construction Manager / Reference Person: Ingenes AG
  • Construction Foreman: Nicolas Zenklusen
  • Construction Foreman STV: Erhard Burgener
  • Foreman: Orlando Truffer
  • Construction time: October 2018 - October 2020
  • Construction costs: 2.5 Mio

Technical specifications:

  • 4'200 m³ excavation
  • 4'250 m³ coffer material
  • 1'600 m² natural stone paving
  • 1'450 m' curbstones / paving slabs
  • 1'750 to of pavement

Object description:

The road body incl. the service lines of the Bealp- and Bahnhofstrasse Naters has been rehabilitated in 8 stages. As a design element, various natural stone pavements have been integrated into the overall concept.

Special requirements:

  • Work under running traffic