Lalden

Renovation shooting range Lisner

  • Client: Municipal administration, 3931 Lalden
  • Construction Manager / Reference Person: FUAG Forum Umwelt AG / Christian Glenz
  • Construction Foreman: Pierluigi D'Onofrio
  • Foreman: Raffaele Gnutti
  • Construction time: November / December 2022
  • Construction costs: CHF 100'000.--

 

Technical specifications:

  • 120 m³ Disposal Inerstoff Type B
  • 150 tons disposal reactor landfill type E
  • 70 to disposal soil washing plant

 

Object description:

The soil in the area of the bullet traps is heavily contaminated with lead in places. The remediation of the ball catchers therefore requires professional dismantling and disposal of the contaminated material in compliance with the law. The remediation work will be carried out by the Volken Group. 120m³ excavated material inert material landfill type B will be disposed of/deposited in our Chalchofen landfill.

 

Special requirements:

  • Very short construction time  
  • Work in steep terrain

Contact person

Pierluigi D'Onofrio

Head of Pollutant Remediation Department /
Head of underlayment department /
Technician HF / Site Manager SBA

+41 27 948 05 14

pierluigi.donofrio@volken-group.ch

Raffaele Gnutti

Foreman