- Client: Canton Valais
- Construction Manager / Reference Person: Dario Micic sbp Ingenieure
- Construction Foreman: Pierluigi D`Onofrio
- Foreman: Orlando Truffer
- Construction time: May 2021 - October 2021
- Construction costs: 750'000.-
Technical specifications:
- 1'100m³ excavated material
- 300m² wall formwork
- 50m² bridge formwork
- 25to reinforcement
- 200m³ concrete
- 350to pavement
Object description:
The existing bridge will be replaced by a new angular skew frame bridge, which has a span of about 4.20m and a width of about 10.30m. The bridge deck as well as the abutment walls are about 0.35 m thick and the abutment walls have a height of 3.20 m. The structure is founded on a continuous base slab about 0.40 m thick and a channel is constructed above it by means of a concrete block camber.
Special requirements:
- Short construction time
- Work in water
- Wall formwork type 4.1
Special features:
- Dewatering
- Creation of temporary detour