- Client: Canton of Valais
- Site management/reference person: Dario Micic sbp Ingenieure
- Site manager: Pierluigi D`Onofrio
- Foreman: Orlando Truffer
- Construction period: May 2021 - October 2021
- Construction costs: 750'000.-
Technical data:
- 1'100m³ excavated material
- 300m² wall formwork
- 50m² bridge formwork
- 25 tons of reinforcement
- 200m³ concrete
- 350 tons of surfacing
Project description:
The existing bridge is being replaced by a new skewed frame bridge with a span of approx. 4.20 m and a width of approx. 10.30 m. The bridge deck and the abutment walls are approximately 0.35 m thick and the abutment walls are 3.20 m high. The supporting structure is founded on a continuous floor slab of approx. 0.40 m thickness and a channel is created above it by means of a concrete block throw.
Requirements:
- Short construction time
- Working in water
- Wall formwork type 4.1
Special features:
- Dewatering
- Creation of temporary detour