Deisch

Residential development Vieux Valais (Kopie) (Kopie) (Kopie) (Kopie)

  • Client: Volken Immobilien
  • Construction Manager / Reference Person: Architektur Kummer AG, Christian Theler
  • Construction Foreman: Jasin Ajeti
  • Foreman: Daniel Helder
  • Construction time: May 2020 - November 2021
  • Construction costs: 2.4 mn.

 

Technical specifications:

  • 3'500 m³ excavation
  • 1'000 m³ backfill/excavation
  • 2'500 m² wall formwork
  • 1'000 m² slab formwork
  • 84'000 kg reinforcement
  • 750 m³ concrete

 

Object description:

In a prime location in the middle of the Aletsch Arena on Riederalp, 2 beautiful vacation homes (buildings E and F) and 3 chalets (J 1, 2 and 3) were built. The development is located in the immediate vicinity of the Hohfluh cable car station and promises a breathtaking view.

 

Special requirements:

  • Mountain construction site 1'905 m.a.s.l.
  • Short construction time
  • Material management
  • Logistics and transport

Contact person

Rafael Millius

Construction Foreman in education

+41 79 533 70 20

+41 27 948 05 48

rafael.millius@volken-group.ch