Herbriggen

Retaining wall along MGBahn

  • Client: Canton of Valais  
  • Construction Manager / Reference Person: Teysseire & Candolfi AG / Nicola Kalbermatten
  • Construction Foreman: Pierluigi D`Onofrio 
  • Foreman: Orlando Truffer
  • Construction time: October 2021 - December 2021
  • Construction costs: 1.3 Mio

Technical specifications:

  • 500 m³ Demolition of retaining wall
  • 2,600 m³ excavation
  • 1,200 m³ Placement of RC gravel mix 0/45
  • 600 to pavement installation 
  • 12 to reinforcement
  • 200 m³ concrete 
  • 123 prefabricated retaining walls à 5to 
  • 1'500 m² exposed masonry sand-lime bricks

Object description:

Demolition of the existing old retaining wall and new construction with precast concrete elements.

Special requirements:

  • Very short construction time 
  • Work during total closure
  • Execution under traffic
  • Precise moving of the prefabricated concrete elements