- Client: Municipality of Embd
- Construction Manager / Reference Person: IBR Ingenieurbüro GmbH
- Construction Foreman: Celine Ludi
- Machinist: Demiri Besir
- Construction time: May 2023 - September 2023
- Construction costs: 0.75 million
Technical specifications:
- 155m construction routes
- Dam center north:
- 930m³ excavation
- 2'700t block throw
- 580 m³ fill material
- North dam:
- 3'140m³ excavation
- 2'560 m³ fill material
- 1'000m² TerraMur facing surfaces
- 12'000m² transverse and longitudinal reinforcement geosynthetics embankment
- 5'400m² application of embankment
Object description:
The project comprises the raising and optimization of two existing earth dams near the village of Kalpetran. The middle north dam was raised with a block throw and the north dam was raised with TerraMur.
Special requirements:
- Access roads to the north dam with a tracked dumper Slope of the construction road up to 30% gradient