- Client: Sägematte Asset AG, Visp
- Construction Manager / Reference Person: Architektur Kummer AG / Sven Tedeschi
- Construction Foreman: Pierluigi D`Onofrio
- Foreman: Francesco D'Onofrio
- Construction time: May 2023 - December 2024
- Construction costs: 7.4 million
Technical specifications:
- 8'000 m³ excavation
- 12'000 m² wall formwork type 2
- 11'000 m² slab formwork type 2
- 650 tons of reinforcement
- 6'500 m³ concrete
- 1000 m² concrete surface winging
- 2'600 m² masonry brick
- 500 m² yellow tub
Object description:
A total of four multi-family houses are available, each housing 3.5, 4.5 and 5.5 room apartments. The apartment buildings are centrally located. Various shopping facilities, post office, sports field and the train station are within walking distance.
Special requirements:
- Short construction time
- Work in groundwater
- Work in the area of traction current installations