- Client: Lonza AG
- Construction management/contact person: Teysseire & Candolfi AG / Nicola Kalbermatten
- Site manager: Iwan Rieder
- Machinist: Manuel Ryter
- Construction period: May – July 2024
- Construction costs: CHF 550,000
Technical data:
- 580 m³ of excavation
- 38 m of utility line construction and drainage channels
- 1 special shaft (retention)
- 210 m³ of concrete floor slab and parapets
- 32 tons of reinforcement
Property description:
In front of the new I09 operations building, a total of eight secured areas (floor slabs) were created as storage areas for hazardous materials.
Requirements:
The work was carried out in the central Lonza/IBEX area. The adjacent roads had to remain open to traffic at all times during the construction work. The construction site had to be set up accordingly and the work coordinated with operations. In addition, the work was carried out in parallel with other work being carried out on building I09.
All construction work was carried out in compliance with Lonza's strict safety regulations (EHS manual).
We received a Safety Award from Lonza for the work. This award stands for safe, clean, and accident-free work, as well as for our high quality in preparation, precise implementation, and efficient communication on this demanding project.