Stalden

échafaudage Killerhofbrücke

  • Client: Canton of Valais
  • Construction management/contact person: SBP Jean – Claude Salzmann
  • Site manager: Uli Rüger / Jose Monteiro
  • Foreman: Gualter Delgado Chagas
  • Construction period: 09.2023-08.2024

Technical data: 

  • Layher Allround / Layher FlexBeam beams            
  • Bridge length 130m          
  • Suspension with 34 SWISS GEWI units pulled at 6.8 tons per SWISS GEWI          
  • 550 m FlexBeam – beams       
  • approx. 2,400 tubular clamps 
  • approx. 23,500 parts
  • approx. 128 tons of material
  • Assembly 2,660 hours

Object description: 

Layher Allround system scaffolding is often used for a wide range of applications, including bridge renovations. With its flexible design and modular construction, the Allround system provides an efficient and safe working platform for construction workers involved in bridge renovation. Allround scaffolding can be used in bridge renovation to provide work platforms for painters, welders, bricklayers, and other tradespeople. The high load-bearing capacity and stability of the system enable it to safely support heavy materials and equipment, which is often required for bridge renovations.
There are many advantages to using Layher Allround systems for bridge renovations:

  • Modularity: The system has a modular design and can therefore be easily adapted to different bridge configurations.
  • Safety: Layher systems are known for their high level of safety and provide a stable working platform for workers to work safely on the bridge.
  • Efficiency: The system can be assembled and dismantled quickly, allowing construction work to be carried out efficiently, which reduces the overall cost of the project.
  • Flexibility: The system can be used for various types of bridge renovations, regardless of the size or shape of the bridge.
  • Reliability: Layher systems are known for their quality and reliability, providing reliable support for bridge renovation work.

Overall, Layher Allround systems are a popular choice for bridge renovations due to their versatility, safety, and efficiency. Layher FlexBeam beams are a special product from Layher that has been developed for applications requiring large spans or unusual shapes. These beams are made of aluminum and are characterized by their light weight and flexibility. They can be used for temporary bridges, stage constructions, grandstands, and other special applications where conventional beam systems may not be suitable. FlexBeam beams make it possible to quickly and easily implement customized solutions for complex scaffolding challenges.p>

Requirements:

  • difficult to access
  • Assembly from one side only
  • Bridge was accessible to traffic during the entire assembly period

Persona di contatto

Ulrich Rüger

Responsabile del reparto ponteggi

+41 27 948 05 84

uli.rueger@volken-group.ch

José Do Lago Monteiro

Project manager e tecnico. Disegnatore ponteggi

Gualter Delgado Chagas

Caposquadra ponteggi