- Client: Canton of Valais
- Construction management/contact person: Edi Abgottspon
- Site manager: Jasin Ajeti
- Foreman: Mario Stilo / Daniel Maric
- Construction period: April 2019 – June 2019
- Construction costs: 295,000
Technical data:
- 300 m console scaffolding
- 150 m² supporting scaffolding
- 500 reinforcement connections, drilling and gluing
- 180 m² formwork
- Approx. 12,000 kg reinforcement
- 80 m³ concrete
Project description:
On the cantonal road leading out of Leuk towards Leukerbad, the existing wall coping was repaired over a length of approx. 300 m in five sections. In some places, the new wall coping was created with a new cantilevered bracket, and in others, the new coping was rebuilt to the width of the wall.
Requirements:
- Continuous traffic lights
- Working in traffic
- Empty/support scaffolding in combination for fall protection & supporting structure
- Working on bracket scaffolding