We maintain strong relationships with partners, suppliers and customers.
Currently, our scaffolders are working on a new building with 11 apartments. The project in Susten was planned by maLro-Immobilien GmbH. In order to build the MFH, the Volken Group excavated around 1500 m3 of earth. A formwork for 5250 m2 was created and about 1300 m3 of concrete with 170 t of reinforcements was poured. In addition, there were about 1000 m2 of masonry with bricks. The construction workers, the foreman and the foreman are a well-coordinated team. They are always working at full speed to finish this project on time.
Are you also planning a new building? The Volken Group is happy to be on site, for both small and large projects.