Before the new Scheitwäge curve near Visperterminen can be renovated, the Volken Group will remove approximately 1,260 m³ of fill material. Afterward, various phases of the project will be undertaken: In addition to a 635 m² sheet pile wall for slope stabilization, a 300 m² dry-stone wall is also planned. This will be supplemented by 245 meters of piping and three inlet and inspection chambers. Only once these structural components are completed will the 296 metric tons of road surfacing be laid. Work began in early June. According to the client, the Canton of Valais (Department of Mobility), the curve is scheduled to be renovated by November 2022.