- Client: Federal Roads Office FEDRO
- Site manager/reference person: Caterina Gianocca, IM Maggia Engineering SA
- Site manager: Celine Ludi
- Foreman: Diego Barberi
- Construction period: September 2024 and August 2025
- Construction costs: 4'500'000.--
Technical data:
- Debris flow material: 3'600 m³
- Roofing material: 1'300 m³
- Excavated foundation: 700 m³
- Concrete NPK D (ceiling): 1,000 m³
- Concrete NPK G: 600 m³
- Shotcrete: 10 m³
- Reinforcement: 300 t
- Prestressed anchors: 51 pcs.
- Seepage pipe: 130 m
- Surfacing: 27 t
Project description:
At the A9 EP ENGI - Engi Gallery construction site, targeted new construction and reinforcement measures are being implemented as part of the immediate measures 2 in order to ensure the load-bearing capacity of sections D and E until the long-term renovation. This includes the installation of new concrete components in the ceiling and load-bearing gallery elements, supplemented by shotcrete work in locally damaged areas. Pre-stressed anchors additionally stabilize the construction. New drainage pipes will be laid to improve drainage. Finally, the roadway was given a new surface layer as a protective layer to ensure the durability and safety of the gallery during operation.
Requirements:
- Working under traffic
- Working under debris flow