Basic development of the western Lonza site

  • Client: Lonza AG Rottenstrasse, Imboden Dominik
  • Site management / reference person: Teysseire und Candolfi AG, Teysseire Philippe
  • Project manager: Erhard Burgener
  • Foreman: Herold Philippona
  • Construction period: 2018-2019
  • Construction costs: 12 million

Technical data:

  • 2,990 m sewerage and drainage system
  • 2,600 m Visper cooling and Rhone water hydrant pipeline
  • 81 shafts
  • 360 m micropiles
  • 30,000 m³ excavation
  • 25,200 m³ basement 0/45
  • 850 m³ concrete
  • 2'000 m² formwork
  • 115 tons of reinforcement

Project description:

Through the implementation of the project, the infrastructure for the future planned buildings of Lonza has been created.

Requirements:

  • Groundwater (dewatering, buoyancy protection)
  • Ongoing traffic Plant site
  • Existing buildings
  • Existing pipelines
  • Tight schedule
  • Minimum gradient