Gamsen

F2 Operational Security 2017-2027 SABA Bildacker

  • Client: ASTRA
  • Construction management/contact person: Pascal Schmid, SPI
  • Site manager: Mathias Wyssen
  • Foreman: Marco Gruber
  • Construction period: May 2020 - September 2020
  • Construction costs: CHF 350,000

Technical data: 

  • 305m³ washed sand             
  • 300m³ drainage gravel 16-32
  • 120m³ gravel mix 8-16

Property description: 

The existing settling basin on the N09 in Gamsen needed to be replaced. To do this, the existing basin was excavated. A new natural settling basin was created using several layers of filter material.

Requirements:

  • Existing material had to be transported to a final landfill site
  • Layer heights had to be maintained
  • Rainwater from the N09 had to be temporarily diverted

Contact person

Mathias Wyssen

HF technician / SBA construction foreman

+41 27 948 05 15

mathias.wyssen@volken-group.ch

Marco Gruber

Foreman