Gampel-Bratsch

HWS Tschingelbach, Lot 3, Gampel-Bratsch

  • Client: Municipality of Gampel-Bratsch
  • Construction management / contact person: INGE Tschingel L2+ / Nikola Vasilic
  • Site manager: Jasin Ajeti
  • Foreman: Alain Ritz
  • Construction period: Mid-June 2023–mid-June 2024
  • Construction costs: 3.0 million

 

Technical data: 

  • 1,200 m³ concrete demolition
  • 285 m³ pavement demolition
  • 6,400 m³ topsoil removal
  • 20,000 m² topsoil application
  • 39,100 m³ excavation
  • 30,000 m³ filling
  • 9,400 m³ removal
  • 320 m³ material delivery
  • 12,365 t stone delivery
  • 860 m³ road foundation layer
  • 415 tons of paving installation
  • 1,150 m² of formwork
  • 46,000 kg of reinforcement
  • 415 m² of concrete

 

Project description:

The construction work basically comprises the implementation of some of the measures required to ensure flood protection on the Tschingelbach stream in Niedergampel in the municipality of Gampel-Bratsch, namely the measures between the cantonal road and the confluence with the Rhone. The following measures were implemented:

  • New construction of site access
  • New construction of culvert in agricultural zone
  • New construction of culvert in Grosser Graben
  • New construction of debris basin 4
  • Widening of the mouth area
  • Underpinning of the cantonal road bridge
  • New construction of the Tschingelbach channel
  • New construction of embankment walls on the left and right
  • New overflow dam

 

Requirements:

  • Material management 
  • Work on open water bodies
  • Some work in groundwater
  • Short construction period

 

Special features:

Material management: Most of the excavated material, fill and topsoil were reused on site.