Saas-Grund

Immediate measures Dutterchi dam

  • Client: Municipality of Saas-Almagell
  • Site management/reference person: Bumann Daniel, IBR Ingenieurbüro GmbH
  • Site manager: Celine Ludi
  • Engineer: Ralf Ebener
  • Construction period: October 2024 and July 2025
  • Construction costs: 245'000.--

Technical data:

  • Length: 160 m
  • Height: 4.00 m
  • Block throw: 1'250 t
  • Excavation: 690 m³
  • Order: 6'640 m³

Project description:

The protective dam was built to protect the residents below the Duttechri ditch from flooding and debris. Two large excavators and a dumper were used for the work. The dam is 160 m long and 4.00 m high. Around 1,250 tons of material were used to throw the blocks. The excavated material amounted to 690 m³, while the total order was 6,640 m³.

Requirements:

  • Immediate measures
  • Working in the mountains
  • Difficult to access
  • Winter interruption