- Client: Canton of Valais
- Construction management/contact person: OBL Canton, Patrick Stoffel / öBL Plannax AG, Joel Mansi
- Site manager: Jasin Ajeti
- Foreman: Alessandro Salemi
- Construction period: June 2022 – June 2024
- Construction costs: 2,300,000
Technical data:
- 8,800 m² demolition of pavement
- 8,500 m³ embankment, installation of fill material
- 6,000 m³ foundation, basement 0/45
- 2,800 m² edging and paving stones
- 1,250 m PP SN16 pipes
- 26 inlet and inspection chambers
- 2,960 tons of surfacing
Property description:
The Swiss main road H19 crosses the construction zone in Bitsch. It is an important main road with an average daily traffic volume of 6,900 vehicles per day. According to the cantonal noise pollution register from 2000, emission limits were exceeded along the H19 in Bitsch. In addition to noise abatement, the project aims to improve traffic safety on the road through Bitsch.
Requirements:
- Traffic light operation
- Work under constant traffic conditions