- Client: Volken Immobilien AG
- Site management/reference person: bpm Schmidt / Peter Schmidt
- Foreman/Polisher: D'Onofrio Antonio / Catherin Diego
- Construction time: April 2016 to April 2017
- Construction costs: CHF 3.5 million
Technical data:
- 400 tons of reinforcement
- 6'000m2 wall formwork
- 6'000m2 slab formwork
- 2'500m2 brick masonry
- 120m2 cement block masonry
- 3'300m3 concrete
- 1'000m2 Layered text
- 300m2 Exposed formwork type 4.
- 600m2 Exposed formwork type 2.1
- 6'000m3 excavation
Project description:
Close to the swimming pool and sports field, on Lavendelweg in Visp, the Binapark II residential development is being built in a 2nd stage. The development consists of 3 apartment buildings (21 residential units). In the basement, all 3 buildings are connected by a large parking garage (33 parking spaces).
Requirements:
- Parking garage in groundwater (white tank waterproofing)
- Walls, ceilings and floor slab in in-situ concrete
- Groundwater lowering
- Balcony ceilings and walls all in exposed concrete