- Client: EW Goms Netze AG
- Site management/reference person: Bruno Margelisch / BMI Architektur AG
- Site manager: Mathias Wyssen
- Foreman: Steiner Erich
- Construction period: August 2023 - April 2024
- Construction costs: 1.85 mio
Technical data:
- 350m³ Misapor
- 2200m² wall formwork type 2
- 280m² exposed concrete 4.1.4
- 140 tons of reinforcement
- 1300m³ concrete NPK C
Project description:
A new EW Goms main building was constructed at the Fiesch entrance. The shell was erected over the winter.
Requirements:
- Fair-faced concrete 4.1.4
- High walls
- Restricted turning radius of construction site crane due to high-voltage lines
Special features:
The shell was erected during the winter months. The high walls in exposed concrete type 4.1.4. required increased effort during the cold season. The excavated material was temporarily stored on a plot of land belonging to the client nearby so that it could be backfilled on site.