Gluringen

Pedestrian crossings

  • Client: Municipality of Goms
  • Site management / reference person: Pascal Schaller
  • Project manager: Erhard Burgener
  • Foreman: Diego Bodenmann
  • Construction period: July 2024 - September 2024
  • Construction costs: 1.1 million

Technical data:

  • 2,400 m² of pavement demolition
  • 2,000 m³ excavation pit
  • 1,850 m³ gravel mix 0/45
  • 660 m' kerbstones
  • 1,000 tons of surfacing

Project description:

A road section of around 200 m was renovated. The substructure was replaced and an existing access road was widened by building a retaining wall and a cantilevered concrete slab.

The work was carried out without disrupting traffic. In the course of the renovations, the client's service lines were newly installed in the road area. At the same time, the telecommunication company and the electricity company installed new utility lines.

Contact persons

Erhard Burgener

Head of Structural & Civil Engineering Department
Member of the Executive Board

+41 27 948 05 06

erhard.burgener@volken-group.ch

Diego Bodenmann

Foreman scaffolding