- Client: Canton of Valais
- Construction management / contact person: Canton of Valais / Martin Sarbach
- Site manager: Jasin Ajeti
- Foreman: Alain Ritz
- Construction period: June – July 2024
- Construction costs: 250,000
Technical data:
- 19 night shifts
- 100 m³ pavement removal
- 650 m³ excavation
- 280 m of SYTEC BaFix S roadside safety barriers
- 1,700 m² of SYTEC TT geogrid supplied and laid
- 900 m³ of RC gravel mix B 0/45 foundation layers
- 190 tons of pavement
- 270 m² topsoil
Project description:
In the Plattji section between Visp and Bürchen, the embankment was renovated and stabilized over a distance of 276 m. The SYTEC BaFix S bank protection system was installed for stabilization. Due to the narrow roadway in the Plattji section, the work had to be carried out at night in several stages.
Requirements
- Material management & logistics
- Tight space constraints
- Night work
- Short construction period
Special features:
- The road had to be reopened to traffic every morning at 4:30 a.m.