- Client: Municipality of Gampel – Bratsch
- Construction management / contact person: INGENES AG – Nikola Vasilic
- Site manager: Jasin Ajeti
- Foreman: Orlando Truffer
- Construction period: January to March 2024
- Construction costs: $400,000
Technical data:
- 55 m³ concrete demolition
- 3,260 m³ excavation
- 2,600 m³ backfilling
- 650 m³ removal
- 900 tons delivery of stones
- 200 m² formwork
- 280 m² counterformwork
- 44,000 kg reinforcement
- 620 m³ concrete
- 2,500 tons block carpet embedded in concrete
Project description:
The construction work includes the creation of scour protection in front of the Schlüüchu barrier. A safety concept was drawn up for the work in the channel, which included a safety plan for natural hazards during the construction phase and had to be strictly adhered to.
The following work was carried out:
- Construction installations
- Construction site access
- Maintenance and operation of water drainage
- Excavation work
- Concrete work, including all necessary winter protection measures
- Creation of concrete-encased block foundations
- Backfilling and embankments
- Dismantling and disposal of temporary water drainage systems
- Demolition of access ramp
- Demolition and restoration of construction installation and landfill sites
- Finishing work
Requirements
- Material management
- Work on open water bodies
- Short construction period