Grengiol's section Windegga-Vogelture

TW Management Stage 7a

  • Client: Municipality of Grengiols
  • Construction management / contact person: Benjamin Zaugg / Rudaz und Partner AG
  • Project manager: Burgener Erhard
  • Foreman: Alexander Heynen
  • Construction period: May 2022 – October 2022
  • Construction costs: $1.8 million

 

Technical data: 

  • 1,600 m pipe length
  • 3,800 m³ excavation
  • 200 m³ rock
  • 1,850 m cable protection pipes
  • 600 tons of pavement

Project description:

Construction of a new ring water pipeline. The pipeline was laid partly in the ground and partly in the existing road.

Requirements:

  • Tight schedule

Special features

As various farms had to remain accessible via the road network at all times, the company proposed an alternative route, which was implemented and thus contributed significantly to ensuring that the project was completed on time and within budget.