Brig

Underlay floor hospital Valais

  • Client: ValaisHospital
  • Site management / reference person: David Bittel ARGE Bauleitung albrecht+amoba Brig
  • Site manager: D'Onofrio Pierluigi
  • Foreman: Agron Selimi
  • Construction period: November 2024 to December 2025
  • Construction costs: CHF 1.60 million

Technical data:

  • 22'000m² impact sound insulation
  • 22'000m² thermal insulation
  • 20'000m edge strips
  • 3'000m² bonded screed
  • 22'000m² floating screed
  • 2'500m² cement screed, terrazzo look
  • 2'500m² priming and sealing

Project description:

The new Valais hospital is being built in Brig. A total of 13 floors are being built.

Requirements:

  • Short construction time
  • High safety precautions
  • The grinding processes were carried out with the utmost precision and know-how.
  • The final impregnation and sealing of the final floor covering in several work steps produces the desired terrazzo floor.

Contact Persons

Pierluigi D'Onofrio

Head of Pollutant Remediation Department /
Head of underlayment department /
Technician HF / Site Manager SBA

+41 27 948 05 14

pierluigi.donofrio@volken-group.ch