A campus that connects the senior and junior schools, the sports hall and the congress center with new sports facilities and green leisure areas.
We spoke to the impressive construction team who gave us an insight into the scope of their work:
- Construction on 3+1 levels
- Underground parking garage with soccer pitch, multi-sports field, padel court and playground above
- 20-strong team, 2 cranes
- Over 4,000 m³ of concrete poured so far
- 210 m³ poured in a single operation (7 concrete truck mixers)
- 40 minutes: one-way journey time from the Leukerfeld plant
- 12 months advance planning for materials
- 2,500 m² slab area per parking level
- Target: 70% completion by December 2025
- 200 m³ of topsoil stored for landscaping