The renovation of the road section near the Matterhorn Gotthard Railway crossing in Mörel-Filet will soon be complete. Voweg AG, a partner company of the Volken Group and Weibel AG, is carrying out the project on the cantonal road. As a base for the pavement, the experienced road builders first lay a fine subgrade to level out the rough subgrade. An eight-centimeter-thick base course is then laid on top of this. It serves a load-bearing function and is produced using the hot-mix method, laid while hot, and compacted with a roller. The work is completed with a binder course, which levels out any unevenness and also serves as the surface course. To ensure this project runs smoothly, five trucks are being used to deliver the mix in multiple trips.
Do you also have a road that needs to be rehabilitated? Our specialists will be happy to do their best for you—even for short sections.