- Client: Municipality of Zermatt
- Construction management/contact person: Amoba Baumanagement / Bruno Umericelli
- Site manager: Iwan Rieder
- Machinist: Marcel Senggen
- Construction period: Stage 1: April to June 2021 / Stage 2: May to June 2024
- Construction costs: CHF 1.1 million
Technical data:
- 9,000 tons of concrete demolition
- 2,200 tons of mixed demolition
- 105 tons of construction waste
- 95 tons of waste wood
- 100 tons of scrap metal
Property description:
The existing Walka Zermatt school complex was replaced in stages by a new building. The three connected buildings with a gymnasium were demolished in two stages. In the first demolition phase in 2021, the old buildings 1 and 2 were demolished. After the new school complex was built, the last building was demolished in 2024.
Requirements:
- The demolition work is being carried out directly in or adjacent to areas of the new school building that are in use and in the middle of a residential neighborhood.
- The newly constructed school building is directly adjacent to the building demolition site of the last stage. Accordingly, the demolition had to be carried out in a controlled manner.
- The work had to be carried out using the lowest-emission methods and with appropriate measures to minimize noise, dust, vibration, and environmental impact.
- With our Volvo EC380HR high-reach demolition excavator and the appropriate attachments, the demolition work was carried out successfully.
- The “Longfront” arm extension was used for the demolition, enabling the demolition excavator to reach an attack height of up to 23 meters.