- Client: Municipality of Riederalp
- Construction management/contact person: Emch + Berger Group
- Site manager: Rafael Millius
- Foreman: Nenad Dugic
- Construction period: May 2020 – November 2021
- Construction costs: CHF 330,000
- Foreman: Nenad Dugic
Technical data:
- 3,500 m³ excavation
- 1,000 m³ backfilling
- 2,500 m² wall formwork
- 1,000 m² ceiling formwork
- 84,000 kg reinforcement
- 750 m³ concrete
Project description:
- Relocation/renewal of drinking water and fire water pipes
- Relocation of a pressure breaker shaft
- Relocation of two pressure reducing valve shafts
- Relocation of a new reservoir
- Relocation of several new hydrants
- Connection of various stables and chalets to the new main pipe
- Laying cable protection pipes for power and data supply
- Relocating cable pull shafts
- Laying sprinkler pipes
Requirements:
- Mountain construction site
- Steep terrain
- Short construction period
- Material management
- Logistics and transport with helicopter and crawler dumper