- Client: Canton of Valais
- Construction management / contact person: OBL – DNSB – Egon Studer / öBL – DNSB – Ralph Tscherry / Technical management – SBP Ingenieure AG – Simon Murmann
- Construction manager: Jasin Ajeti
- Foreman: Alain Ritz
- Construction period: Sept. – November 2023
- Construction costs: 496,000
Technical data:
- 3,600 m³ foundation layers RC gravel mix B 0/45
- 1,200 tons of pavement
Property description:
The new Basperstrasse industrial area project is intended to replace the old Basperstrasse in the Raron industrial zone. The industrial zone will be bypassed to the north and east and connected to the road at both ends. In a further phase, it will serve to connect the eastern headquarters and the GERA pumping station.p>