Bitsch

Ring line Äbnet - z'Matt

  • Client: Municipality of Bitsch
  • Site management/reference person: Renato Berchtold, Rolf Ritz
  • Site manager: Jasin Ajeti
  • Foreman: Alessandro Salemi
  • Construction period: September 2022 - November 2022
  • Construction costs: 300'000.-

Technical data:

  • Approx. 560m³ trench excavation in loose rock
  • Approx. 300m³ rock excavation
  • Lay approx. 350m of cast iron pipes
  • Lay approx. 2'000m² of soil

Project description:

The Volken Group is laying a drinking water pipeline over 350 meters. The steep terrain and soil conditions make the work difficult, which is why a walking excavator from Menzi Muck is being used to remove soil and clear rocks. Protective measures are required to protect hikers and road traffic below the pipeline.

Requirements:

  • Working on steep terrain up to 70°
  • Protective measures for hikers and the cantonal road
  • Short construction time

Special features:

  • Material preparation for pipe coating with screening bucket on site