- Client: Municipality of Riederalp
- Construction management / contact person: Ingenieur-/ & Planungsbüro Schnydrig Gmbh / Simon Schnydrig
- Construction manager: Jasin Ajeti
- Foreman: Daniel Helder
- Construction period: Phase 1: October–November 2021 / Phase 2: July–November 2022
- Construction costs: 400,000
Technical data:
- 880 m³ Excavation/ & earthworks
- 655 m³ fillings & backfilling
- 1,300 m² topsoil
- 750 tons of stone delivery for channel, base, and bank reinforcement
- 690 m² channel, bed and bank reinforcement
- 100 m² milling, breaking and mixing of solid road surface
Project description:
The construction work includes the implementation of the necessary measures to ensure flood protection in the Teiffe Bach West area on the Riederalp, as part of the advanced measures of stages 1 and 2. The main work includes demolition work, the construction of culverts, the relocation of pipes and terrain adjustments. The project also includes the delivery of stones and blocks for the design of the channels, bed, and bank areas, the expansion of channels, and the reinforcement of the bed and banks. In addition, a ford will be built in the area of the hiking trail and a temporary guide dam will be erected.
Requirements
- Material management & logistics
- Work on open waterways
- Mountain construction site
- Short construction period
Special features
- Material management on mountain construction sites