- Client: Gommerkraftwerke AG
- Site management/reference person: Urban Paris, PAP Paris und Partner AG
- Site manager: Celine Ludi
- Foreman: Diego Bodenmann
- Construction period: July 2024 and July 2025
- Construction costs: 1'500'000.--
Technical data:
Various repair work:
- Block throw
- Pressure pipe
- Power line
- Road
Object description:
Significant damage was found on the GWK system after the storm. The pressure line was carefully exposed, covered with sand and then put back into operation. Three large excavators and a large dumper were used for the work. The river was given a new boulder bed on both sides to secure the banks. The debris was crushed on site and reinstalled. The power line and the road were also repaired.
Requirements:
- Immediate measures
- Difficult to access
- Winter interruption