Binntall

Immediate measures Binntall

  • Client: Gommerkraftwerke AG
  • Site management/reference person: Urban Paris, PAP Paris und Partner AG
  • Site manager: Celine Ludi
  • Foreman: Diego Bodenmann
  • Construction period: July 2024 and July 2025
  • Construction costs: 1'500'000.--

Technical data:

Various repair work:

  • Block throw
  • Pressure pipe
  • Power line
  • Road

Object description:

Significant damage was found on the GWK system after the storm. The pressure line was carefully exposed, covered with sand and then put back into operation. Three large excavators and a large dumper were used for the work. The river was given a new boulder bed on both sides to secure the banks. The debris was crushed on site and reinstalled. The power line and the road were also repaired.

Requirements:

  • Immediate measures
  • Difficult to access
  • Winter interruption

 

 