- Client: Tierarztpraxis am Rottu AG
- Construction management/contact person: Architektur Kummer AG Architekten GmbH
- Site manager: Thomas Imhof
- Deputy site manager: Iwan Rieder
- Foreman: Gabriel Wyssen
- Construction period: March 2024 to end of July 2024
- Construction costs: 750,000 CHF
Technical data:
- 1,000 m² ceiling formwork
- 1,200 m² wall formwork
- 50 tons of reinforcement
- 400 cubic meters of concrete
- 550 m² masonry
Property description:
The existing building was completely and professionally cleared of asbestos-containing material and then completely demolished. The excavation work was then carried out and the shell of a new five-storey building was quickly erected.
Requirements:
- Short construction time
- Limited space
- Compliance with safety and environmental protection requirements
- On-time implementation