Zermatt

Excavation work and construction of new Blatten water reservoir, Zermatt

  • Client: Municipality of Zermatt
  • Site management/reference person: Brantschen Gerhard, LABAG AG
  • Site manager: Celine Ludi
  • Foreman: Marco Gruber
  • Machine operator: Goran Aleksic
  • Blasting foreman: Ilic Budimko
  • Construction period: May 2023 to November 2024
  • Construction costs: 1.5 million

Technical data:

  • 1'300m³ removal of humus
  • 11,750m³ excavation of rock (blasting work)
  • 5'000m³ preparation of rock Material for concrete production
  • 40m² nail wall
  • 44 pcs. Anchors
  • 4 pcs. Micropiles
  • 1'900m² wall formwork
  • 800m² slab formwork
  • 230 tons of reinforcement
  • 1'350m³ concrete
  • 650m² mono concrete floor slab

Project description:

The excavation for the new Blatten water reservoir in Zermatt was carried out in the 2023 construction season. A total of 11,750 m³ of rock had to be blasted and transported to an interim storage facility. Of this quantity, 5,000 m³ of rock was crushed using a crushing plant and then sorted using a screening plant. The material was divided into three components and served as the raw material for the concrete work for the 2024 construction season. At the start of the 2024 season, a mobile concrete plant was installed to produce all the concrete for the construction of the reservoir directly on site.

Requirements:

  • Blasting work
  • Mobile concrete plant
  • Difficult accessibility
  • Short construction time
  • High demands on concrete