New artificial turf sports field

  • Client: FC Termen / Ried-Brig
  • Site management / Reference person: SPI Schmidhalter Partner Ingenieure / Iwan Rieder
  • Site manager: D'Onofrio Pierluigi
  • Foreman: Cathrein Diego
  • Construction time: May 2019 to August 2019
  • Construction costs: CHF 500,000

Technical data:

  • 4,500 m3 excavation / removal
  • 250 m3 Excavated trenches
  • 1,700 m3 Gravel 16/45
  • 250 m3 St. Jacob's mixture 0/22
  • 4,500 m2 Bentonite mat
  • 260 m edge closures
  • 260 m cable protection pipes
  • 650 m drainage pipes
  • 80 tons of asphalt
  • 85 m3 structural concrete
  • 8 tons of reinforcement

Project description:

The location of the football pitch is defined by the width of the pitch with a safety margin and the existing space between the road and the existing sports field. Retaining walls in in-situ concrete were built to compensate for the differences in height. The entire football pitch is irrigated with a sprinkler system and drained with drainage pipes. Underneath the artificial turf and the elastic layer, a St. Jakob layer was laid using an asphalt paver with a tolerance of + - 10mm.

Requirements:

  • Leveling accuracy below artificial turf Structure